Over the past few months, our future hydroelectric power station has taken some decisive steps forward:
- Water intake: the civil engineering is complete, and the gates are being installed. Lifting of nozzles and impoundment scheduled for this summer.
- Penstock: laid, buried, connected to the building - pressure tests underway.
- Building: structural work completed, framework and overhead crane being installed. Joinery to arrive in June.

Next steps:
- Rehabilitation of the plots
- Turbine delivery and installation
- Electrical and automation work
🎯 Objective: commissioning in October!

🙏 A big thank you to all the companies involved in the field, often in demanding weather conditions. Their professionalism drives the energy transition forward in concrete ways, day after day.

Key figures:
- Power: 840 kW
- Flow rate: 2.5 m³/s
- Head: 42 m
- Annual production: 2.8 GWh
- Consumption equivalent: 560 households